everymegawatt
 PRO
LIVE · AI DATA-CENTER POWER

The scarce asset in AI isn’t the GPU.
It’s power.

A live tape of the companies racing to energize AI — every SEC filing and reputable report, screened to the signals that move the thesis: new gigawatts secured, offtake deals, financing. GPUs can be financed in months; interconnection queues run years. Every megawatt will be monetized.

13 companies tracked/SEC filings + screened press/refreshed 5× daily/latest 2026-08-28

Scoreboard

power controlled by company · as of 2026-08-04 · click a row for sites · a column to sort
CompanyOperational MW Secured MW Pipeline MW Total GW
IRENIREN· 9 sites8103,3901,6005.80
CIFRCipher Digital· 7 sites2107004,3905.30
HUTHut 8 Corp.· 4 sites7101,3302,2304.27
APLDApplied Digital Corporation· 6 sites1802,1101,5003.79
CORZCore Scientific, Inc.· 6 sites3501,2101,4703.03
BTDRBitdeer Technologies Group· 16 sites1,4701,3501803.00
NBISNebius Group N.V.· 7 sites2202,40002.62
RIOTRiot Platforms, Inc.· 5 sites1,26060001.86
GLXYGalaxy Digital Inc.· 4 sites1301,50001.63
WULFTeraWulf Inc.· 6 sites604609901.51
SLNHSoluna Holdings, Inc.· 13 sites120808301.03
NUAINew Era Energy & Digital, Inc.· 2 sites001,0001.00
CRWVCoreWeave, Inc.· 3 sites0000.00

Power tiers (operational / secured / pipeline) and the all-in total are the human-gated power position. Financials are deliberately excluded here — they aren't comparable across strategies (colocation vs. AI cloud vs. vertically integrated); see a company profile for its economics.

The Tape

103 events · 13 companies · latest 2026-08-28

Summaries & signal tags are AI-generated from primary sources and may contain errors — each item links to the original.

Demand side
Yesterday · 2026-08-28
IRENPress
BLUE OWL MANAGED FUNDS LEAD $2.4 BILLION AI FACTORY FINANCING FOR IRENMATERIAL
Blue Owl managed funds are leading a $2.4 billion AI factory financing for IREN.
Large-scale financing for an AI factory signals capital flowing to data center buildout, a leading indicator of future contracted power demand.
$2.4B raised
PR Newswire
5 days ago · 2026-08-24
NBISSEC
Foreign-issuer report (6-K)NOTABLE
Nebius Group N.V. closed a private offering of convertible senior notes, issuing 0.50% notes due 2030 and 4.50% notes due 2034.
Low-cost convertible notes (0.5%–4.5%) bolster Nebius's capital to secure and energize scarce data-center power capacity, tightening future supply.
0.5%4.5%
Also covered bySEC 6-K
SEC 6-K
Aug 20 · 2026-08-20
CRWVNews
Hudson River Signs Multibillion-Dollar CoreWeave Deal for AI CloudMATERIAL
Hudson River signed a multibillion-dollar deal with CoreWeave for AI cloud services.
Multibillion-dollar AI cloud deal signals demand but lacks MW, location, or timeline, providing no direct signal for contracted power capacity near fiber.
Bloomberg.com
Aug 19 · 2026-08-19
NBISSEC
Foreign-issuer report (6-K)MATERIAL
Nebius Group announced a proposed private offering of $4.50 billion of convertible senior notes, to fund data center build-out, AI cloud development and GPU procurement, with concurrent exchange agreements for existing notes.
NBIS raises $4.5B in convertible debt to fund data center and AI cloud expansion, signaling a major capital commitment to secure future capacity.
$5.0B raised2%3%
Also covered bySEC 6-K
SEC 6-K
Aug 17 · 2026-08-17
IRENNews
Iren delivers first phase of AI capacity to Microsoft in TexasMATERIAL
IREN delivered the first phase of AI capacity to Microsoft in Texas.
IREN's first-phase delivery to Microsoft validates contracted, energized AI capacity in Texas, reinforcing the scarcity of near-fiber power.
$9.7B contract
Also covered byNews · The Block
Data Center Dynamics
NUAISEC
Current report (8-K)MATERIAL
New Era reported increased combined capacity for Phases 1 & 2 to 757 MW, advanced PPA negotiations for Phase 1, construction permits received, and $270M undrawn under its Macquarie facility.
Increased gross capacity and advanced PPA negotiations signal strong demand and execution, aligning with the thesis of MW scarcity near fiber.
SEC 8-K
Aug 16 · 2026-08-16
RIOTNews
Bitcoin Miner Riot Platforms Just Signed a $9 Billion Compute Deal With Anthropic. Why AI Is Now the Key to Valuing Bitcoin Mining Stocks.MATERIAL
Riot Platforms signed a $9 billion compute deal with Anthropic.
Bitcoin miner pivoting existing powered sites to AI compute validates that energized MW with fiber are the scarce asset now being repriced via hyperscaler-grade contracts.
$9.0B contract
The Globe and Mail
Aug 14 · 2026-08-14
CORZSEC
Current report (8-K)MATERIAL
Core Scientific completed the acquisition of Polaris DS for ~$444M, securing 440 MW of operational power capacity and advancing its Muskogee campus expansion plan to 1.5 GW gross power. The deal also includes a potential $40M earn-out for an additional 40 MW of firm capacity by year-end 2026.
Securing 440 MW of operational power capacity and advancing to 1.5 GW gross power at Muskogee underscores the strategic value of energized, contracted MW near fiber.
→ unnamed
Also covered byNews · The Globe and Mail
SEC 8-K
NUAISEC
Quarterly report (10-Q)MATERIAL
New Era Energy & Digital disclosed its flagship Texas Critical Data Centers (TCDC) campus is designed to support over 1 GW of potential compute capacity, with projected power delivery beginning as early as end of 2027. The company also secured a $290 million senior secured term loan facility and completed a public offering raising approximately $107.5 million to fund development.
The 1 GW capacity and secured financing signal strong commitment to development, aligning with the thesis of energized, contracted MW near fiber being the scarce asset.
$20M raised
Also covered bySEC 10-Q/A
SEC 10-Q
RIOTSEC
Current report (8-K)MATERIAL
Riot Platforms entered into a $573.0 million senior secured delayed-draw term loan facility to fund long-lead equipment and related expenses for its 191 critical IT MW data center project at the Rockdale Facility.
RIOT debt-raise for 191 MW IT data center signals that power capacity is being repurposed from mining to AI-ready assets even before tenant commitments, tightening available power.
$9.1B contract$573M raised
Also covered byNews · Barron'sNews · CoinDeskNews · theblock.coNews · Bloomberg.comNews · CNBC
SEC 8-K
Aug 13 · 2026-08-13
IRENSEC
Current report (8-K)MATERIAL
IREN delivered its first 50MW liquid-cooled AI cloud deployment (Horizon 1) to Microsoft under a $9.7 billion contract and targets expansion to 480MW in 2026 and 1.2GW in 2027, while achieving NVIDIA Exemplar Cloud status.
First 50MW liquid-cooled AI cloud deployment to Microsoft under a $9.7B contract signals strong demand and financial commitment for high-capacity, AI-optimized data center power.
$9.7B contract$38.80M/MW-yr
Also covered byPress · GlobeNewswire
SEC 8-K
RIOTNews
Riot Platforms Re-Wires the Ledger for a $9B AI Power PlayMATERIAL
Riot Platforms is involved in a $9 billion AI power initiative, a significant development for its AI data-center power business.
RIOT's $9B pivot from bitcoin mining to AI data centers signals that flexible, grid-connected power assets can be re-priced for high-value compute loads—a shift invisible in traditional financials.
$9.0B contract
The Globe and Mail
SLNHSEC
Quarterly report (10-Q)▲ BULLISH · Q2 2026
SLNH disclosed multiple materially significant developments: acquisition of the 150 MW Briscoe Wind Farm, energization and ramp-up of the 83 MW Project Kati 1, formation of a joint venture with Metrobloks for the up to 350 MW AI-focused Project Kati 2, multiple financing transactions including an amended credit agreement and senior secured notes, and consolidation of full ownership in Project Dorothy 1B, creating a vertically integrated 50 MW generation‑to‑compute chain.
SLNH's vertical integration and secured capacity near fiber strengthens its position in the AI power market, aligning with the thesis of energized, contracted MW near fiber being the scarce asset.
$53M contract
Also covered byEarnings · SEC 8-K
SEC 10-Q
Aug 12 · 2026-08-12
CRWVSEC
Quarterly report (10-Q)MATERIAL
The company disclosed 393 MW of undelivered power at a single data center site expected in phases in 2026 and 2028, 355 MW undelivered at other sites expected between 2026 and 2028, and a service agreement for up to 78 MW to be delivered in phases.
Undelivered MW at a single site (393 MW) signals concentrated, contracted capacity pipeline—the scarce asset—even without a named hyperscaler or GAAP revenue.
→ unnamed
SEC 10-Q
NBISSEC
Foreign-issuer report (6-K)MATERIAL
Nebius raised approximately $4.8 billion through equity sales and pre-funded warrants, added $4.4 billion in new debt, and completed an acquisition that added $605.6 million in goodwill.
Nebius's $4.8B equity and $4.4B debt raise strengthens its capacity to secure future power, but no contracted MW or fiber-linked asset is disclosed.
$4.4B raised
Also covered bySEC 6-K
SEC 6-K
Aug 11 · 2026-08-11
CRWVEarnings
Current report (8-K)▲ BULLISH · Q2 2026
CoreWeave reported active power capacity grew to 1.5 GW (up ~500 MW) and contracted power now stands at 3.7 GW. The company also raised over $10 billion in unsecured debt/convertible bonds and a $3.1 billion term loan, plus a $1 billion strategic investment from Jane Street.
CoreWeave’s contracted power doubling to 3.7 GW signals massive future capacity absorption, but the $13.1B debt raise shows the capital intensity required to energize it.
$13.1B raised5.5%
Also covered bySEC 8-K
SEC 8-K
Aug 10 · 2026-08-10
BTDRSEC
Foreign-issuer report (6-K)MATERIAL
Bitdeer announced a $4.7 billion, 16-year AI/HPC colocation lease for its Tydal, Norway site, updated multiple capacity timelines and projects, and disclosed $517.3 million in financing proceeds from borrowings and its ATM program.
A 16-year, $4.7B lease with a leading AI lab for 121 IT MW in Norway signals hyperscale demand for contracted, energized capacity near fiber, validating the scarcity premium.
$4.7B contract$2.43M/MW-yr
Also covered bySEC 6-KSEC 424B5SEC F-3ASR
SEC 6-K
GLXYSEC
Quarterly report (10-Q)MATERIAL
Galaxy’s Helios campus has 133 MW of critical IT load (200 MW gross) operational under a 15-year lease with CoreWeave, with ERCOT approving over 1.6 GW total. Another 600 MW will support 393 MW for CoreWeave Phase II/III starting Q2 2027, leaving 830 MW uncontracted.
Long-term lease with CoreWeave locks in 133 MW operational IT load, proving contracted MW near fiber are scarce and valuable.
SEC 10-Q
RIOTEarnings
Current report (8-K)▲ BULLISH · Q2 2026
Riot Platforms executed a landmark 20-year, 191 MW data center lease with a leading frontier AI lab for $9.1 billion in total contract revenue, and completed delivery of the initial 25 MW to AMD, with a second 25 MW under construction, totaling 241 MW contracted. The company also secured $573 million in interim financing from Morgan Stanley.
The 20‑year AI lease at 3× the AMD rate locks ~4× more contracted MW, proving hyperscale-like demand classifies colo capacity as the new scarce asset, not spot mining.
$9.1B contract$2.27M/MW-yr$573M raised
Also covered byNews · Data Center DynamicsNews · Bloomberg.comNews · Bloomberg.comNews · Barron'sNews · The BlockNews · Bloomberg.comNews · Barron'sPress · Riot Platforms |SEC 10-Q
SEC 8-K
Aug 5 · 2026-08-05
BTDRSEC
Foreign-issuer report (6-K)MATERIAL
Bitdeer signed a $4.7 billion, 16-year colocation lease with Volta for 121 IT MW at its Tydal, Norway campus, with Phase 1 energization by end-2026 and Phase 2 by Q1 2027, and plans to raise debt for the ~$500M remaining capex.
121 MW of contracted, soon-to-be-energized colocation capacity in Norway locks in long-term fiber-adjacent power, validating that firm, scalable IT MW are the real scarcity in AI DC markets.
$4.7B contract$2.43M/MW-yr
Also covered byNews · The Globe and MailSEC 6-K
SEC 6-K
GLXYSEC
Current report (8-K)MATERIAL
Galaxy expanded its total data center power pipeline to over 5.7 GW through site acquisitions, delivered 133 MW Phase I to CoreWeave under a 15-year lease, and completed a $3.5 billion debt offering to fund Phase II construction, with Phase I expected to generate ~$80M/quarter at over 90% margin starting Q3 2026.
Galaxy's 133 MW IT delivery to CoreWeave under a 15-year lease proves contracted, energized capacity near fiber is converting pipeline into high-margin (~90%) recurring revenue, a signal GAAP capex obscures.
$3.5B raised
SEC 8-K
WULFEarnings
Current report (8-K)▲ BULLISH · Q2 2026
TeraWulf reports 102 MW operational, 336 MW under construction, a 20-year ~$19B lease with Anthropic for 401 MW, acquisition of a 1 GW site, and $530M monetization of Abernathy JV. Liquidity stands at $3.0B.
The 20-year, $19B Anthropic lease for 401 MW at Justified Data Campus underscores the value of secured, energized MW near fiber, reinforcing the thesis.
$19.0B contract$2.37M/MW-yr
SEC 8-K
Aug 4 · 2026-08-04
BTDRPress
Bitdeer Announces $4.7 Billion, 16-Year AI/HPC Data Center Lease for Tydal, Norway CampusMATERIAL
Bitdeer announced a $4.7 billion, 16-year lease for an AI/HPC data center campus in Tydal, Norway.
A 16-year, $4.7B lease signals long-term contracted cash flows, but the absence of MW, counterparty, and timeline details leaves the critical 'energized MW near fiber' thesis unvalidated.
$4.7B contract
GlobeNewswire
CIFREarnings
Current report (8-K)▲ BULLISH · Q2 2026
Cipher accelerated delivery of initial capacity at Black Pearl, secured an option for a new 900 MW site (Apollo) in Texas, and completed project-level financing to fully fund the Stingray data center development.
Accelerated delivery and a new 900 MW option signal speed-to-fiber execution, converting contracted MW into cash-flowing assets faster than the market prices.
Also covered byNews · The Globe and MailSEC 10-Q
SEC 8-K
CRWVNews
CoreWeave to Enter Asian Market With Indonesian Data CentersMATERIAL
CoreWeave announces plans to build data centers in Indonesia, marking its entry into the Asian market.
Announcement lacks MW, counterparty, or timeline, offering no signal on scarce contracted power near fiber.
Also covered byPress · CoreWeave
Bloomberg.com
HUTEarnings
Current report (8-K)▲ BULLISH · Q2 2026
Hut 8 reported major milestones: 949 MW of contracted AI data center capacity with $26.6B in expected base-term contract value, $7.5B in project financing closed, and a second 352 MW IT lease at Beacon Point signed post-quarter, commercializing the full 1 GW campus.
Hut 8's fully commercialized 1 GW Beacon Point campus with investment-grade tenant and robust project financing underscores the thesis of MW near fiber as a scarce asset.
$26.6B contract$5.04M/MW-yr$7.5B raised→ unnamed
Also covered bySEC 10-Q
SEC 8-K
HUTNews
Hut 8 shares slip after mild Q2 revenue miss as AI data center pipeline growsNOTABLE
Hut 8 reported a Q2 revenue miss while indicating its AI data center pipeline is expanding.
Expanding AI data center pipeline signals potential future lock-up of energized, contracted MW near fiber, intensifying scarcity.
The Block
IRENSEC
Current report (8-K)MATERIAL
IREN completed the acquisition of Mirantis, a cloud software and services provider, for approximately 12.6 million shares plus $40 million in cash and other consideration, strengthening its vertically integrated AI Cloud platform.
Adds software layer atop IREN’s owned DCs to deepen vertical integration and capture more AI workload economics, but adds zero energized MW to the scarce power thesis.
Also covered byPress · GlobeNewswire
SEC 8-K
Aug 3 · 2026-08-03
HUTNews
NVIDIA’s Reported $50B Lease and the Nuclear-Powered AI FactoryMATERIAL
Headline reports a $50B lease deal by NVIDIA for a nuclear-powered AI factory, indicating a major data center power offtake.
A $50B GPU cloud lease with NVIDIA signals hyperscale offtake for massive, behind-the-meter nuclear power deployed at AI factory scale, validating the scarce asset thesis.
$50.0B contract
Data Center Frontier
Jul 29 · 2026-07-29
CORZSEC
Current report (8-K)MATERIAL
Routine filing, nothing material.
Routine 8-K with no power-related disclosures; a non-event for the AI data-center power thesis.
SEC 8-K
Jul 28 · 2026-07-28
APLDNews
APLD Q4 Earnings Call Highlights Contracted AI ExpansionMATERIAL
APLD announces contracted AI expansion during Q4 earnings call.
A contracted AI expansion reported in earnings confirms conversion of pipeline to lease, moving MW from speculative to secured, which the market may not yet price into net asset value.
The Globe and Mail
CORZEarnings
Current report (8-K)▲ BULLISH · Q2 2026
Core Scientific announced a major AMD partnership with up to 2.5 GW of leasable capacity anchored by 530 MW of 15-year agreements, increased total leased customer power capacity to ~1.1 GW, and is billing 437 MW. The company also raised substantial debt ($4.3B proceeds) and significantly increased capex and liquidity.
The AMD partnership secures long-term, high-capacity power deals, reinforcing CORZ's position in the scarce asset of energized, contracted MW near fiber.
$14.0B contract$373k/MW-yr$4.3B raised7.75%
Also covered byNews · The Globe and MailNews · The Globe and MailNews · ReutersSEC 8-KPress · Core ScientificNews · CoinDeskSEC 10-Q
SEC 8-K
GLXYPress
Galaxy Expands Data Center Footprint with Acquisition of 500 Acre Campus in McGregor, TexasNOTABLE
Galaxy acquires a 500-acre campus in McGregor, Texas for data center expansion.
Land acquisition signals future buildout that will compete for scarce power capacity and fiber-connected sites.
galaxy.com
GLXYSEC
Current report (8-K)MATERIAL
Galaxy Helios Data Centers II LLC entered into an indenture for 9.875% Senior Secured Notes due 2031, which includes a covenant requiring the issuer to maintain operational control of at least 195 MW of data centers in the United States.
The covenant ensures GLXY maintains a significant operational footprint, aligning with the thesis that energized, contracted MW near fiber are the scarce asset.
9.875%
SEC 8-K
HUTNews
Nvidia revealed as tenant for $50bn data centre that will use its chipsMATERIAL
Nvidia is revealed as a tenant in a new $50 billion data center, indicating a major lease deal for AI compute capacity.
Nvidia's tenancy signals high demand for AI compute, validating the thesis that energized, contracted MW near fiber are scarce assets.
$50.0B contract
Also covered byNews · Reuters
Financial Times
Jul 27 · 2026-07-27
APLDEarnings
Current report (8-K)▲ BULLISH · Q4 FY2026
Applied Digital signed three new 15-year take-or-pay leases totaling 810 MW with a hyperscaler, adding ~$20 billion in base-term contracted revenue, and closed $2.15 billion and $1.59 billion senior secured notes offerings. The company also energized Phase 1 of Building 2 (75 MW) at Polaris Forge 1, bringing live capacity to 175 MW, and has secured 1.4 GW of contracted critical IT load across five campuses.
Three 15-year hyperscaler leases convert 810 MW of pipeline into ~$20B of contracted backlog, proving that energized, fiber-connected sites can lock in investment-grade revenue streams at scale.
$36.2B contract$1.71M/MW-yr$3.7B raised6.75%7%
Also covered bySEC 10-K
SEC 8-K
Jul 22 · 2026-07-22
GLXYSEC
Current report (8-K)MATERIAL
Galaxy Digital's indirect subsidiary announced a $3.507 billion private offering of senior secured notes to fund a 400 MW utility / 260 MW critical IT data center project in Dickens County, Texas.
Secured debt funding for 260 MW IT capacity in Texas signals capital markets are underwriting contracted, fiber-adjacent power as collateral, not just a corporate promise.
$3.5B raised
Also covered bySEC 8-KPress · PR Newswire
SEC 8-K
GLXYNews
Galaxy Digital Seeks $3.5 Billion Debt for Texas Data CenterMATERIAL
Galaxy Digital is seeking $3.5 billion in debt financing for a Texas data center.
A $3.5B debt raise signals capital markets are underwriting future contracted cash flows, validating the thesis that financed, fiber-connected MW are the binding constraint.
Bloomberg.com
NUAISEC
Current report (8-K)NOTABLE
NUAI secured a waiver and consent from lender Macquarie that extends the deadline to establish a $100 million at-the-market (ATM) equity program under its term loan agreement.
Extension of ATM equity deadline provides liquidity but does not signal incremental contracted power capacity.
SEC 8-K
Jul 21 · 2026-07-21
BTDRSEC
Foreign-issuer report (6-K)MATERIAL
Bitdeer updates power capacity pipeline with new AI cloud lease in Malaysia (21.7 MW) and colocation lease in Norway, along with energization delays at Massillon and timelines for other sites.
The 10-year lease for 21.7 MW IT capacity in Malaysia underscores the strategic importance of securing long-term, high-quality power near fiber for AI workloads.
SEC 6-K
IRENNews
IREN’s $2.8B AI Deals Highlight New Funding ModelMATERIAL
IREN reported $2.8 billion in AI deals.
The $2.8B in AI deals underscores IREN's strategic shift towards monetizing power assets, aligning with the thesis that energized, contracted MW near fiber are the scarce asset.
$2.8B contract
Data Center Knowledge
Jul 20 · 2026-07-20
HUTSEC
Current report (8-K)MATERIAL
Hut 8 fully commercialized its 1 GW Beacon Point AI data center campus with a second 15-year, 352 MW IT lease to a high-investment-grade tenant, doubling contracted capacity at the campus to 704 MW and raising total portfolio contracted IT capacity to 949 MW. The lease has a $9.8 billion base-term contract value, pushing campus-level contract value to $19.6 billion, with initial energization on track for Q1 2027.
A second 15-year, 352 MW IT lease to a high-IG tenant at a single campus proves that contracted, energized MW near fiber are the scarce asset commanding hyperscale rents.
$26.6B contract$1.87M/MW-yr→ unnamed
Also covered byNews · Data Centre MagazineNews · The BlockPress · PR NewswireNews · ReutersNews · The Globe and MailNews · CoinDeskNews · Data Center DynamicsNews · CoinDesk
SEC 8-K
HUTNews
IREN, Hut 8 Soar On AI Data Center Deals, Lead Neocloud RallyMATERIAL
Hut 8 is soaring due to AI data center deals, indicating a concrete deal development.
Signals a market re-rating for a neocloud securing AI demand, but the tracker needs the missing MW, counterparty, and timeline to confirm it adds contracted, near-fiber capacity to the scarce asset pool.
Investor's Business Daily
IRENSEC
Current report (8-K)MATERIAL
IREN announced $2.8bn in new customer contracts, raising its ARR target to over $4bn, with 480MW of AI cloud capacity being delivered this year and 1.2GW targeted for 2027.
IREN's secured contracts and prepayments signal strong demand and financial stability, reinforcing the thesis that energized, contracted MW near fiber are the scarce asset.
$2.8B contract→ unnamed
Also covered byNews · Data Center Dynamics
SEC 8-K
IRENNews
Iren’s stock surges as the neocloud lands $2.8 billion worth of new dealsMATERIAL
IREN's neocloud lands $2.8 billion worth of new deals.
The $2.8B in deals validates hyperscale demand for neocloud services, underscoring the value of contracted power capacity even absent disclosed MW.
$2.8B contract
Also covered byNews · Investor's Business Daily
MarketWatch
IRENNews
Hut 8, IREN land billions in new contracts, lifting AI compute stocks MARA, RIOT, WULFMATERIAL
IREN landed new contracts worth billions.
New billions-scale contracts signal hyperscaler demand for IREN’s energized sites, validating the thesis that contracted power near fiber is the scarce asset.
Also covered byNews · CoinDesk
CoinDesk
WULFNews
AI compute stocks bounce as Hut 8, IREN land billions in new contractsMATERIAL
Hut 8 and IREN secured contracts worth billions, indicating major new deal flows for those AI data-center providers.
The deals signal strong demand for AI data-center power, reinforcing the thesis that energized, contracted MW near fiber are the scarce asset.
CoinDesk
Jul 17 · 2026-07-17
NBISSEC
6-K/A filingMATERIAL
Nebius secured a $775 million senior secured term loan facility to finance the buildout of its AI cloud.
Securing $775M in senior debt signals capital-market conviction in AI cloud buildout, validating the thesis that power-linked infrastructure attracts large-scale funding.
$775M raised
SEC 6-K/A
NBISSEC
Foreign-issuer report (6-K)MATERIAL
Nebius raises $775 million in senior secured debt financing backed by GPU infrastructure and contracted cash flows from an investment-grade customer, with a repeatable framework for over $40 billion of additional customer commitments.
Nebius secures debt financing backed by contracted cash flows from investment-grade hyperscalers, signaling strong demand and financial viability of GPU-powered AI infrastructure.
$775M raised
SEC 6-K
Jul 16 · 2026-07-16
SLNHSEC
Current report (8-K)NOTABLE
Soluna appointed former Microsoft hyperscale AI data center executive Ryan Carver as Chief Development Officer to lead its expanding AI infrastructure platform.
Hyperscaler veteran hire signals credible path to contracting scarce fiber-proximate power for AI data centers, a leading indicator invisible in financials.
SEC 8-K
Jul 14 · 2026-07-14
SLNHSEC
Current report (8-K)NOTABLE
Soluna's monthly update discloses that Project Kati 2 (350+ MW AI/HPC) has signed a Letter of Intent with a potential tenant, and construction on Project Kati 1B Phase 2 (9 MW) achieved substantial completion ahead of schedule. Existing Bitcoin hosting sites remain at full capacity.
A 350+ MW AI/HPC LOI signals future fiber-adjacent capacity absorption, but the unnamed tenant and pre-lease stage mean no contracted, energized MW yet.
→ unnamed
SEC 8-K
Jul 6 · 2026-07-06
WULFSEC
Current report (8-K)MATERIAL
TeraWulf signed a 20-year, 401 MW lease with Anthropic for HPC at its Kentucky campus, with phased delivery beginning late 2027, and announced the sale of its equity in FS CS I LLC for $530 million.
The 20-year lease of 401 MW to Anthropic underscores the value of secured, energized capacity near fiber, aligning with the thesis of scarce MW assets.
SEC 8-K
Jun 29 · 2026-06-29
BTDRSEC
Foreign-issuer report (6-K)MATERIAL
Bitdeer signed a colocation lease agreement for an AI data center site in Tydal, Norway.
Bitdeer signing a colocation lease in Norway signals an emerging AI load in a fiber-rich, hydropower market, potentially tightening Nordic Power availability.
SEC 6-K
Jun 26 · 2026-06-26
APLDSEC
Current report (8-K)MATERIAL
Applied Digital entered into a credit agreement dated May 29, 2026, for refinancing and general corporate purposes. The filing also reveals a subsidiary named 1.21 Gigawatts, LLC, indicating a 1.21 GW power capacity.
The 1.21 GW capacity indicates a significant power asset, but without a clear counterparty or contract, it's unclear how this aligns with the thesis of scarce, contracted MW near fiber.
SEC 8-K
Jun 18 · 2026-06-18
BTDRSEC
Foreign-issuer report (6-K)MATERIAL
Bitdeer is in advanced colocation negotiations for its Tydal, Norway site, deployed new NVIDIA GB300 clusters, and provided updates on several energized and pipeline projects including 50 MW completed in Ethiopia and timelines for Ohio sites.
The energized 50 MW site in Ethiopia and the 570 MW under contract in Ohio highlight the strategic importance of secured MW near fiber for AI and cloud infrastructure.
Also covered bySEC Form 6-K / GlobeNewswire
SEC 6-K
CRWVSEC
Current report (8-K)NOTABLE
CoreWeave issued 8.500% Senior Notes due 2032 under the indenture dated June 18, 2026, a financing event.
CoreWeave's 8.5% note issuance funds data center buildout, intensifying competition for contracted power near fiber.
8.5%
SEC 8-K
Jun 17 · 2026-06-17
SLNHSEC
8-K/A filingMATERIAL
Soluna Holdings acquired 100% of Briscoe Wind Farm, a 150 MW operational wind project in Texas, for $53 million, with all related debt settled at closing.
Acquisition of operational wind farm with existing PPA underscores strategic control of energized MW, aligning with the thesis of scarce assets near fiber.
$53M contract
SEC 8-K/A
Jun 16 · 2026-06-16
APLDSEC
Current report (8-K)MATERIAL
APLD issued 7.000% Senior Secured Notes due 2031, likely to finance the 150MW ELN-04 data center project, which is subject to a datacenter lease with CoreWeave.
APLD secures 7% debt to fund a 150MW data center leased to CoreWeave, aligning with the thesis of contracted MW near fiber as a scarce asset.
6.75%7%
Also covered bySEC 8-K/A
SEC 8-K
NBISSEC
Foreign-issuer report (6-K)MATERIAL
Nebius completed its acquisition of Eigen AI, an inference and model optimization company, strengthening its full-stack AI cloud platform.
Nebius deepening its AI cloud platform via Eigen acquisition signals growing need for specialized compute, likely increasing future demand for contracted data center power.
SEC 6-K
Jun 15 · 2026-06-15
CIFRSEC
Current report (8-K)MATERIAL
Cipher Digital's indirect subsidiary Stingray Compute LLC issued 6.000% Senior Secured Notes due 2031, with a requirement for a Qualified Operator having at least 475 MW of data center capacity experience, suggesting a large-scale data center project.
The financing and operator requirement signal a large-scale, credible data center project, aligning with the thesis of MW near fiber being a scarce asset.
6%
SEC 8-K
Jun 11 · 2026-06-11
CRWVSEC
Current report (8-K)MATERIAL
CoreWeave announces intention to offer $3.5 billion in senior notes due 2032, with proceeds for general corporate purposes including debt repayment.
CoreWeave's debt raise signals financial flexibility for expansion, but lacks specifics on power capacity or contracts.
$3.5B raised
SEC 8-K
Jun 10 · 2026-06-10
HUTSEC
Current report (8-K)MATERIAL
Beacon Point DC LLC entered into an indenture for the issuance of 6.129% Senior Secured Notes due 2042.
6.129% long-dated secured debt signals capital-market appetite to fund data-center power infrastructure, enabling scarce energized MW ahead of GAAP capacity.
6.129%
SEC 8-K
Jun 9 · 2026-06-09
APLDSEC
Current report (8-K)MATERIAL
Applied Digital announced a $1.59 billion senior secured notes offering to fund 150 MW of critical IT load at its Ellendale AI factory campus and repay a bridge loan, alongside a $350 million revolving credit facility and a lease assignment MOU with CoreWeave.
150MW IT load secured by lease with CoreWeave is being funded via $1.59B debt, showing deep capital markets appetite for contracted AI DC capacity.
$36.0B contract$1.6B raised7%
Also covered bySEC 8-KSEC 8-K
SEC 8-K
SLNHSEC
Current report (8-K)MATERIAL
Soluna Holdings formed a joint venture (Soluna MB KK II JVCO, LLC) to develop data center projects in Willacy County, Texas, with planned capacity of 100 MW (Phase I) and 250 MW (Phase II). Soluna will contribute approximately $19.08 million for Phase II property acquisition.
Announced IT capacity without offtake or timeline signals potential future supply but lacks the contracted, near-fiber scarcity that drives value.
SEC 8-K
Jun 8 · 2026-06-08
CIFRSEC
Current report (8-K)MATERIAL
Cipher Digital announced a private offering of $810 million senior secured notes due 2031 through its subsidiary Stingray Compute LLC.
The $810M debt raise signals capital markets are funding AI data-center buildout, validating the thesis that contracted power assets can attract large-scale financing.
$810M raised6%
Also covered bySEC 8-K
SEC 8-K
Jun 4 · 2026-06-04
HUTSEC
Current report (8-K)MATERIAL
Hut 8's subsidiary announced a $4.25 billion senior secured notes offering to finance a 352 MW turnkey data center project in Texas, which will be leased to a high-investment-grade tenant.
HUT secures $4.25B in debt to fund a 352 MW data center leased to a high-investment-grade tenant, aligning with the thesis of contracted MW near fiber as a scarce asset.
$4.3B raised6.129%→ unnamed
Also covered bySEC 8-KSEC 8-K
SEC 8-K
Jun 1 · 2026-06-01
IRENSEC
Current report (8-K)MATERIAL
IREN subsidiary entered into $3.6 billion financing agreements (term loan and senior notes) to fund GPU infrastructure for a Microsoft cloud services contract in Childress, Texas.
Securing $3.6B in debt for a Microsoft-backed GPU deployment validates that hyperscaler-committed power capacity can attract large-scale, investment-grade-linked infrastructure capital.
$3.6B raised5.96%
SEC 8-K
May 26 · 2026-05-26
IRENSEC
Current report (8-K)MATERIAL
IREN signed a $1.6 billion GPU supply agreement with Dell to support its previously announced $3.4 billion AI cloud contract at its Childress, Texas campus.
The deal underscores the strategic importance of securing GPU supply to support large-scale AI cloud contracts, aligning with the thesis that energized, contracted MW near fiber are crucial.
$3.4B contract→ unnamed
SEC 8-K
WULFSEC
Current report (8-K)MATERIAL
TeraWulf acquired the Muskie Data Campus in Kentucky, a site capable of supporting up to 1 GW of data center capacity, with initial 500 MW delivery starting in H2 2028 and the remaining 500 MW in H2 2030.
1 GW site with transmission access but no offtake highlights the scarcity of contracted, investment-grade capacity near fiber.
SEC 8-K
May 20 · 2026-05-20
NBISSEC
Foreign-issuer report (6-K)MATERIAL
Nebius disclosed a major capacity agreement for ~250MW guaranteed / ~328MW installed across three 10-year phases, with aggregate fees up to $2.6 billion. The filing also shows significant financing activity including $4.34 billion in convertible notes and $2.0 billion from pre-funded warrants.
The deal secures significant guaranteed capacity with long-term financing, aligning with the thesis of MW near fiber being a scarce asset.
$2.6B contract$4.3B raised
SEC 6-K
SLNHSEC
Current report (8-K)NOTABLE
Soluna Digital Inc. is acquiring the remaining 49% membership interest in Soluna DV ComputeCo, LLC for $8.77 million, giving it 100% ownership of the data-center compute subsidiary.
The acquisition consolidates full ownership of the compute subsidiary, enhancing control over MW assets but does not directly impact the POWER thesis metrics.
SEC 8-K
May 19 · 2026-05-19
NUAISEC
Current report (8-K)MATERIAL
New Era Energy & Digital provided a Q1 2026 business update detailing significant progress on its flagship 1.4 GW Texas Critical Data Center (TCDC) campus, including a phased power development pathway, a definitive agreement to acquire adjacent land for power optimization, and a secured funding pathway with an $80M+ cash position and a Macquarie credit facility.
The phased expansion and secured funding pathway highlight the strategic importance of near-term MW availability and long-term scalability in the power-constrained Texas market.
→ unnamed
Also covered bySEC 424B3
SEC 8-K
May 18 · 2026-05-18
CRWVSEC
Current report (8-K)MATERIAL
CoreWeave Financing DDTL V, LLC, a subsidiary of CoreWeave, Inc., entered into a $3.1 billion term loan credit agreement to fund infrastructure acquisitions and liquidity requirements.
A $3.1B debt raise signals that lenders are underwriting CoreWeave’s contracted, fiber-adjacent capacity as collateral, validating the thesis that such assets are financeable scarce resources.
$3.1B raised
SEC 8-K
SLNHEarnings
Current report (8-K)▲ BULLISH · Q1 2026
Soluna completed 48 MW Project Kati 1A ahead of schedule, advanced a 100+ MW AI partnership with Metrobloks for Kati 2, acquired a 150 MW wind farm for $53M to power a planned 300 MW AI campus, and expanded its pipeline to 4.3 GW.
Soluna's rapid expansion and strategic partnerships underscore the value of secured MW near fiber, aligning with the thesis of power as a scarce asset.
SEC 8-K
May 15 · 2026-05-15
NUAISEC
Quarterly report (10-Q)MATERIAL
Company acquired remaining interests in TCDC, a 438-acre Texas campus with over 1 GW potential compute capacity and an initial 250 MW gas-fired power plant and data center, with power delivery projected by end of 2027. Acquisition funded partly by a $50M convertible note.
The acquisition of TCDC consolidates a strategic asset with significant power and compute capacity, aligning with the thesis of MW near fiber being scarce.
$50M raised
Also covered bySEC S-3/A
SEC 10-Q
May 14 · 2026-05-14
BTDRSEC
Foreign-issuer report (6-K)MATERIAL
Bitdeer disclosed a global power portfolio of approximately 3.0 GW, advanced negotiations for a colocation tenant at its Tydal AI data center, and a $69M annualized AI Cloud run-rate, signaling material progress in its AI infrastructure pivot.
BTDR's 3.0 GW power portfolio, with 1,744 MW online and 1,259.5 MW in pipeline, underscores the strategic value of secured MW near fiber, aligning with the thesis.
$568M raised→ unnamed
Also covered bySEC 6-K
SEC 6-K
IRENSEC
Current report (8-K)MATERIAL
IREN issued 1.00% Convertible Senior Notes due 2033 with an initial conversion rate of 13.6848 Ordinary Shares per $1,000 principal amount, representing a financing event.
IREN's 1% convertible notes provide low-cost capital to fund data-center expansion, a leading indicator of future contracted MW near fiber.
1%
SEC 8-K
May 13 · 2026-05-13
NBISSEC
Foreign-issuer report (6-K)MATERIAL
Nebius announced it has secured up to 1.2 GW of power and land for a new, owned AI factory in Pennsylvania, a major capacity expansion.
NBIS securing 1.2 GW of power underscores the critical importance of large-scale, secured power capacity for AI infrastructure, aligning with the thesis of power scarcity.
SEC 6-K
May 11 · 2026-05-11
IRENEarnings
Current report (8-K)▲ BULLISH · Q3 FY26
IREN announced a major strategic partnership with NVIDIA including a $2.1B investment and a $3.4B AI Cloud contract, alongside detailed 2026/2027 capacity expansion plans targeting 480MW and 1,210MW respectively, and the acquisition of Nostrum Group adding 490MW of secured power in Spain.
IREN's strategic partnership with NVIDIA and capacity expansion plans underscore the value of secured, energized MW near fiber, aligning with the thesis.
$3.4B contract$562k/MW-yr
SEC 8-K
IRENSEC
Current report (8-K)MATERIAL
IREN launched a $2 billion convertible notes offering (plus $300 million option) to raise capital for general corporate purposes and capped call transactions.
Convertible note raise signals capital-market access for power-intensive digital infra, even absent a specific PPA or MW announcement.
$2.6B raised1%
Also covered bySEC 8-K
SEC 8-K
SLNHSEC
Prospectus (424B)MATERIAL
Soluna acquired a 149.85 MW wind farm in Texas for $53M and secured $12.5M in new debt financing for the deal, while also raising $12M via an unsecured note to fund the buyout of its Dorothy 1A data center project.
Acquiring a 149.85 MW wind farm and securing debt financing aligns with the thesis of securing energized, contracted MW near fiber.
$25M raised
SEC 424B3
May 8 · 2026-05-08
GLXYSEC
Prospectus (424B)MATERIAL
Galaxy Digital's Helios data center campus in West Texas has 1.6 GW of ERCOT-approved gross power capacity, with 133 MW critical IT load (200 MW gross) under a 15-year lease to CoreWeave expected by mid-2026, and an additional 393 MW critical IT load (600 MW gross) under Phase II/III leases starting in 2027; 830 MW remains uncontracted.
CoreWeave's long-term lease of 133 MW IT load (200 MW gross) and future phases underscores the value of secured, fiber-connected power capacity in ERCOT.
Also covered bySEC 424B3SEC 10-Q
SEC 424B3
GLXYEarnings
Current report (8-K)▼ BEARISH · Q2 2026
Routine filing, nothing material.
Routine 8-K with no disclosed power capacity, counterparty, or contract; a non-event for the scarce-asset thesis.
Also covered bySEC S-3SEC S-3ASR
SEC 8-K
NUAISEC
Registration statement (S-3)MATERIAL
The filing discloses a flagship data center campus (TCDC) with over 1 GW of potential compute capacity and projected power delivery starting as early as end of 2027.
1 GW of planned IT capacity in Texas with a 2027 delivery timeline adds to the future power pipeline but lacks near-term contracted, energized MW critical for scarcity.
SEC S-3
WULFEarnings
Current report (8-K)▲ BULLISH · Q1 2026
TeraWulf reports 60 MW of operational critical IT HPC capacity for Core42, near-term delivery of additional capacity, a major site acquisition adding 480 MW, and a new $250M revolving credit facility, while reaffirming its growth strategy targeting 250-500 MW of new contracted capacity annually.
Operational IT capacity and major site acquisition underscore WULF's strategic focus on securing and expanding energized, contracted MW near fiber.
$250M raised
Also covered byEarnings · SEC 8-K (earnings release)SEC 10-Q
SEC 8-K
May 7 · 2026-05-07
CRWVEarnings
Current report (8-K)▲ BULLISH · Q1 2026
CoreWeave reported record Q1 2026 with $99.4B revenue backlog, surpassed 1 GW active power, secured $21B Meta deal and Anthropic agreement, and closed NVIDIA's $2B investment and $8.5B loan facility.
CoreWeave's secured and projected power capacity, along with major deals and financing, underscores the value of energized, contracted MW near fiber.
$21.0B contract$8.5B raised
Also covered bySEC 10-QSEC / CoreWeave 8-K
SEC 8-K
IRENEarnings
IREN reports Q3 FY26 results: $144.8M revenue, $247.8M net loss▲ BULLISH · Q3 2026
IREN announced a $3.4bn AI Cloud contract with NVIDIA, a 5GW strategic partnership, expansion to 480MW in 2026, 1,210MW in 2027, 5GW secured power for 2028+, and has $2.6bn cash plus financing initiatives to fund capex.
IREN's secured 5GW power portfolio and NVIDIA contract underscore the value of contracted, energized MW near fiber, aligning with the thesis.
$9.7B contract$388k/MW-yr
Also covered byEarnings · SEC 8-KSEC 10-Q
SEC 8-K
SLNHSEC
Current report (8-K)MATERIAL
Soluna provided a monthly business update highlighting significant progress on AI/HPC data center projects, including a 300+ MW development (Dorothy 3) with an interconnection study underway and a 300+ MW project (Kati 2) with active hyperscaler discussions and design work started. The company also closed a $53M acquisition of a wind farm for vertical integration.
Projects Dorothy 3 and Kati 2 highlight Soluna's focus on large-scale, AI/HPC-ready MW capacity, aligning with the thesis of energized, contracted MW near fiber being the scarce asset.
→ unnamed
SEC 8-K
May 6 · 2026-05-06
CORZSEC
Current report (8-K)MATERIAL
Routine filing, nothing material.
Routine filing with no material power facts provides zero signal for the scarce asset thesis.
Also covered bySEC 8-K
SEC 8-K
CORZEarnings
Current report (8-K)▲ BULLISH · Q1 2026
Core Scientific expanded its total gross power capacity pipeline to 4.5 GW, closed a $233 million land-and-power acquisition in Hunt County for ~430 MW, billed 243 MW of colocation capacity at a $350 million annualized revenue run-rate, and completed a $3.3 billion senior secured note offering.
The Hunt County acquisition and expanded capacity pipeline underscore the strategic importance of securing large, energized MW near fiber, aligning with the thesis.
$3.3B raised7.75%
Also covered bySEC 10-Q
SEC 8-K
CORZSEC
Current report (8-K)MATERIAL
Core Scientific announced a merger agreement to acquire Polaris DS LLC and its subsidiaries, including Polaris Technology Inc. and Skymax Technology LLC, with $120 million in deposits made.
Merger to acquire Polaris DS signals CORZ is scaling data-center footprint, but no MW, counterparty, or power contract specifics were disclosed.
SEC 8-K
HUTSEC
Quarterly report (10-Q)▲ BULLISH · Q1 2026
Hut 8 reports Beacon Point campus with approvals for up to 1,000 MW of utility capacity and initial phase of 352 MW IT load; River Bend 330 MW utility capacity under construction; Energy Capacity Under Development reached 1,230 MW; closed $3.25 billion senior secured notes offering on April 30, 2026; and sold Far North JV power assets of 310 MW for $75.4 million.
HUT secures significant utility capacity and funding, aligning with the thesis that energized, contracted MW near fiber are the scarce asset.
$9.8B contract$1.74M/MW-yr$3.3B raised6.192%
Also covered byEarnings · SEC 8-K
SEC 10-Q
May 5 · 2026-05-05
APLDSEC
Current report (8-K)NOTABLE
Applied Digital completed the separation of its cloud business into ChronoScale, a new publicly traded company, retaining 97% ownership and investing $15.75 million. This strategic move separates the data center hosting platform from the cloud compute layer.
The separation of the cloud business into a new entity signals a strategic shift, but does not directly impact the power thesis as no specific power deal details are provided.
SEC 8-K
CIFRSEC
Current report (8-K)MATERIAL
Cipher Digital signed a third AI data center campus lease with an investment-grade hyperscale tenant, secured a $200 million revolving credit facility, and reported that development at its Barber Lake and Black Pearl data centers is on schedule.
Third lease with an investment-grade hyperscaler signals deepening demand for contracted data center capacity, reinforcing the scarcity value of energized MW near fiber.
$200M raised→ unnamed
SEC 8-K
Apr 30 · 2026-04-30
RIOTSEC
Riot reports Q1 2026: revenue $167.2M beats, first data center revenue $33.2MMATERIAL
AMD exercised an option for an additional 25 MW, bringing total contracted critical IT capacity with Riot to 50 MW, marking a significant expansion and validation of Riot's data center operations.
AMD's expansion of contracted capacity to 50 MW signals strong demand for Riot's data center power, validating the thesis of energized, contracted MW near fiber as a scarce asset.
SEC 8-K
Apr 27 · 2026-04-27
CORZSEC
Core Scientific to expand Pecos, TX campus to ~1.5 GW gross (1.0 GW leasable)MATERIAL
Core Scientific announced a multi-tiered strategy to scale its Pecos, Texas campus to approximately 1.5 GW of gross power (1.0 GW leasable).
Announced 1.0 GW leasable IT capacity at a single site signals massive future supply, but without a counterparty or timeline, it remains unsecured inventory, not scarce contracted power.
SEC Form 8-K (Exhibit 99.1)
Apr 22 · 2026-04-22
CORZSEC
Core Scientific prices $3.3B of 7.750% senior secured notes due 2031MATERIAL
Core Scientific is restructuring to issue senior secured notes and has disclosed a massive, contracted data-center pipeline: ~590 MW of critical IT capacity 100% licensed to CoreWeave across six facilities, with ~900 MW of grid capacity secured, ~350 MW energized, and over 185 MW billing as of March 2026. The filing details specific MW allocations, site-level operational status, and a $10 billion aggregate revenue estimate.
590 MW of IT capacity fully contracted to CoreWeave at premium rates, secured by 900 MW of grid access, signals locked-in, fiber-adjacent power scarcity value ahead of energization milestones.
$10.0B contract$3.3B raised7.75%
SEC Form 8-K (Exhibit 99.1)
Apr 16 · 2026-04-16
CRWVSEC
CoreWeave completes $1.75B 9.750% senior notes due 2031 offeringMATERIAL
CoreWeave completed a $1 billion add-on senior notes offering, bringing total 9.750% notes due 2031 to $2.75 billion, with proceeds for general corporate purposes including debt repayment.
CoreWeave's significant debt raise signals strong financial flexibility and capacity for future expansion, aligning with the thesis of securing capital for power-intensive operations.
$1.0B raised9.75%
SEC 8-K
Apr 8 · 2026-04-08
APLDSEC
Applied Digital reports fiscal Q3 2026 results: revenue up 139% to $126.6MMATERIAL
APLD reports a fully operational 100 MW AI data center, breaks ground on a new 300 MW campus, and secures $2.15B in financing for a 200 MW hyperscaler campus, while also restructuring CoreWeave leases with credit enhancements.
APLD secures significant financing and a long-term lease for its 200 MW Polaris Forge 2 campus, reinforcing the value of energized, contracted MW near fiber.
$2.1B raised6.75%
SEC 8-K
Mar 2 · 2026-03-02
RIOTSEC
Riot posts record 2025 revenue of $647.4M, cites $1.9B liquidity for buildoutMATERIAL
Riot reports a nearly two-gigawatt power portfolio and the commencement of the first phase of its data center lease with AMD, generating revenue as of January 2026.
Riot's nearly 2 GW power portfolio and operational lease with AMD underscore the value of secured, energized MW near fiber.
SEC 8-K
Feb 24 · 2026-02-24
BTDRSEC
Bitdeer issues $325M 5.00% convertible notes due 2032, repurchases 2029 notesMATERIAL
Bitdeer Technologies Group issued $325 million (with an option for an additional $50 million) of 5.00% Convertible Senior Notes due 2032.
Self-mined bitcoin colo converts electricity into HPC-adjacent digital commodity, bringing non-hyperscaler demand to fiber-connected sites absent a utility PPA.
$325M raised5%
SEC Form 6-K
Feb 4 · 2026-02-04
CIFRSEC
Black Pearl Compute prices $2.0B of 6.125% senior secured notes due 2031MATERIAL
Cipher Mining priced a $2.0 billion senior secured notes offering through its subsidiary Black Pearl Compute, providing major financing for the company.
Debt financing provides capital for Cipher's data-center buildout but lacks detail on the specific power or fiber assets being funded.
$2.0B raised6.125%
SEC 8-K
Jan 15 · 2026-01-15
GLXYSEC
Galaxy secures ERCOT approval for added 830 MW at HeliosMATERIAL
Galaxy Digital received ERCOT approval for an additional 830 MW of computing load at its Helios data center campus in West Texas, materially expanding its power capacity.
ERCOT approval for 830 MW at Helios underscores the growing scarcity and strategic value of large-scale, grid-connected power capacity.
SEC 8-K